What is an Indiana lien waiver?
An Indiana lien waiver is a signed document in which a contractor, subcontractor, supplier or equipment provider gives up some or all of its mechanic's lien rights on a property, usually in exchange for a payment. Indiana's mechanic's lien law is in Chapter 3 of Article 28 of Title 32 of the Indiana Code.
Indiana limits how early a waiver can be demanded. On most projects, a contract cannot force you to give up lien or payment bond rights before you are paid, and it cannot make you promise not to file a lien notice at all.
- All four waiver types: conditional or unconditional, on a progress payment or the final payment
- A bold warning on unconditional waivers and a cleared-funds condition on conditional ones
- Exceptions for retention, unpaid extras and change orders, or disputed claims on a final waiver
- Optional payment bond release, subcontractor payment statement, indemnity and notary block
- Business or individual claimants, with a named signer and title for a company
Indiana lien waiver rules
Indiana lien waivers at a glance
| Topic | Rule | Source |
|---|---|---|
| Waiver before payment | A contract term requiring a waiver of lien or payment bond rights before payment is void | Ind. Code § 32-28-3-16 |
| No-lien promises | A contract term agreeing not to file a notice of intention to hold a lien is void | Ind. Code § 32-28-3-16 |
| Exclusions | Class 2 structures and auxiliary improvements, and listed utility property | Ind. Code § 32-28-3-16 |
| If you are not paid | Sworn statement and notice of intention filed with the county recorder within 90 days after last furnishing; 60 days for a Class 2 structure | Ind. Code § 32-28-3-3 |
| Notice to owner | The recorder mails a copy to the owner within three business days | Ind. Code § 32-28-3-3 |
Read on a mirror of the Indiana Code marked current as of January 1, 2026. Class 2 structure is defined in Ind. Code § 22-12-1-5.
Our builder treats Indiana as a state without a statutory waiver form. We read the waiver and filing sections above but not every section of the chapter, so check any form a payer hands you against the payment it covers.
Conditional or unconditional, progress or final
- Conditional progress: send it with a pay application; it releases rights for work through a stated date once that payment clears
- Unconditional progress: sign it after a progress payment has cleared
- Conditional final: send it with your final invoice; it releases everything except listed disputes once the last payment clears
- Unconditional final: the last document on the job, signed only when the final payment is in your account
A conditional waiver fits Indiana's rule well. It lets the payer collect paperwork with a pay application while your rights stay intact until the money arrives.
How LawVault handles Indiana
For Indiana, the builder prints the full waiver. It names the claimant, owner, customer and property, describes the work and the payment, and states the payment condition or the bold unconditional notice. Progress waivers keep retention, unpaid extras and change orders outside the release, and final waivers carve out any disputed claims you list.
You can add a release of payment bond rights, a statement that you have paid your own subcontractors and suppliers, an indemnity, and a notary acknowledgment.
An unconditional waiver gives up your Indiana lien rights the moment you sign it, and the 90-day or 60-day filing window keeps running while you wait. LawVault is a document service, not a law firm, and this page is not legal advice. An Indiana construction lawyer can review a waiver on a disputed job.
How to create your Indiana lien waiver
- Pick the waiver typeChoose Indiana, then conditional or unconditional, on a progress payment or the final payment.
- Enter your detailsAdd your name or business, your role on the job and your address.
- Describe the projectName the owner, the job address and county, who hired you and the work you furnished.
- Describe the paymentEnter the amount, who is paying and, for a progress waiver, the through date.
- List exceptions and extrasKeep retention, extras or disputed claims out, and choose any optional terms or a notary block.
- Sign and deliverDownload the PDF or Word file, sign it and give it to the payer. Keep a copy.
Indiana lets you trade lien rights for payment you actually receive. Match each waiver to one payment, keep conditional and unconditional versions straight, and file every signed copy with your job records.
Common questions
Generally no. Ind. Code § 32-28-3-16 voids a provision in a contract to improve Indiana real estate that requires a laborer, supplier or equipment provider to waive lien rights, or payment bond claims, before being paid. A promise not to file a notice of intention to hold a lien is void too. The section does not apply to Class 2 structures or to certain utility property.
Our builder treats Indiana as a state without a statutory waiver form and drafts a complete waiver. Section 32-28-3-16 restricts when a waiver can be demanded but does not set its wording. If a payer insists on its own form, compare it line by line with the payment it covers.
Section 32-28-3-16 does not require it. Our builder offers an optional notary acknowledgment because many owners, lenders and title companies ask for one.
A conditional waiver takes effect only once the payment clears. An unconditional waiver gives up your lien rights when you sign it, even if the payment later fails. Sign unconditional waivers only for money already in your account.
Under Ind. Code § 32-28-3-3, the sworn statement and notice of intention to hold a lien must be filed with the county recorder within 90 days after you last performed labor or furnished materials, or within 60 days for a Class 2 structure.
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your lien waiver
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this lien waiver: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.