What is a Kentucky lien waiver?
A Kentucky lien waiver is a signed document in which a contractor, subcontractor or supplier gives up some or all of its lien rights under KRS Chapter 376, usually in exchange for a payment. Kentucky does not write a waiver form into its statutes, but it does limit what a construction contract can make you give up.
Under KRS 371.405, a contract term that strips away your Chapter 376 lien rights is void. The statute carves out one kind of waiver: a partial waiver given for a progress payment. That is the everyday waiver that travels with a pay application.
- All four waiver types: conditional or unconditional, on a progress payment or the final payment
- A bold warning on unconditional waivers and a cleared-funds condition on conditional ones
- Exceptions for retention, unpaid extras and change orders, or disputed claims on a final waiver
- Optional payment bond release, subcontractor payment statement, indemnity and notary block
- Business or individual claimants, with a named signer and title for a company
Kentucky lien waiver rules
Kentucky lien waivers at a glance
| Topic | Rule | Source |
|---|---|---|
| Contract waivers of lien rights | Void and unenforceable as against public policy | KRS 371.405(2)(b) |
| Exception | Partial lien waivers given by a contractor or subcontractor for progress payments | KRS 371.405(2)(b) |
| Contracts covered | Construction contracts entered into after June 26, 2007 | KRS 371.405(1) |
| Severability | A void provision does not undo the rest of the contract | KRS 371.405(4) |
Read on a mirror of the Kentucky Revised Statutes marked current as of January 1, 2025, and in the 2025 SB 76 bill text, which keeps subsection (2)(b) unchanged.
Our builder treats Kentucky as a state without a statutory waiver form. KRS 371.405 speaks to provisions in construction contracts. How it applies to a standalone final waiver signed at the end of a job is a question for a Kentucky lawyer, so this page does not answer it.
Conditional or unconditional, progress or final
- Conditional progress: send it with a pay application; it releases rights for work through a stated date once that payment clears
- Unconditional progress: sign it after a progress payment has cleared
- Conditional final: send it with your final invoice; it releases everything except listed disputes once the last payment clears
- Unconditional final: the last document on the job, signed only when the final payment is in your account
A partial waiver for a progress payment is the type KRS 371.405 expressly protects. Keep each one tied to a single payment and a single through date.
How LawVault handles Kentucky
For Kentucky, the builder prints the full waiver. It names the claimant, owner, customer and property, describes the work and the payment, and states the payment condition or the bold unconditional notice. Progress waivers keep retention, unpaid extras and change orders outside the release, and final waivers carve out any disputed claims you list.
You can add a release of payment bond rights, a statement that you have paid your own subcontractors and suppliers, an indemnity, and a notary acknowledgment.
An unconditional waiver gives up your Kentucky lien rights the moment you sign it. If the payment fails, you may be left chasing the debt without a lien. LawVault is a document service, not a law firm, and this page is not legal advice. Talk to a Kentucky construction lawyer before signing a final waiver on a disputed job.
How to create your Kentucky lien waiver
- Pick the waiver typeChoose Kentucky, then conditional or unconditional, on a progress payment or the final payment.
- Enter your detailsAdd your name or business, your role on the job and your address.
- Describe the projectName the owner, the job address and county, who hired you and the work you furnished.
- Describe the paymentEnter the amount, who is paying and, for a progress waiver, the through date.
- List exceptions and extrasKeep retention, extras or disputed claims out, and choose any optional terms or a notary block.
- Sign and deliverDownload the PDF or Word file, sign it and give it to the payer. Keep a copy.
Kentucky protects the routine progress waiver and little else in a construction contract. Match each waiver to one payment, keep conditional and unconditional versions straight, and file every signed copy with your job records.
Common questions
Generally no. KRS 371.405(2)(b) says a provision in a construction contract that waives, releases or extinguishes rights under KRS Chapter 376, the lien chapter, is against public policy, void and unenforceable. The one exception is a partial lien waiver given by a contractor or subcontractor for a progress payment.
KRS 371.405 applies to construction contracts entered into after June 26, 2007.
Our builder treats Kentucky as a state without a statutory waiver form and drafts a complete waiver. KRS 371.405 limits waiver provisions but does not set waiver wording. If a payer insists on its own form, compare it line by line with the payment it covers.
KRS 371.405 does not require it. Our builder offers an optional notary acknowledgment because some owners, lenders and title companies ask for one.
A conditional waiver takes effect only once the payment clears. An unconditional waiver gives up your lien rights when you sign it, even if the payment later fails. Sign unconditional waivers only for money already in your account.
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your lien waiver
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this lien waiver: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.