What is an Alaska mechanic's lien?
Alaska Statutes §§ 34.35.050 to 34.35.120 let people who furnish labor, materials, services or equipment for a private project claim a lien when they are not paid. The recorded document is a claim of lien, verified under oath, with the contents listed in AS 34.35.070.
Alaska’s system turns on two optional notices: the owner’s notice of completion, which can shorten the recording window to 15 days, and the claimant’s notice of right to lien, which protects the longer window and shifts the burden of proof. Public projects do not use liens; claimants there rely on payment bonds.
Alaska mechanic's lien rules
Alaska claim of lien at a glance
| Topic | Rule | Source |
|---|---|---|
| Document | Claim of lien | AS 34.35.070 |
| Notice of right to lien | Optional, before furnishing; shifts the burden on owner consent | AS 34.35.064 |
| Recording deadline | 120 days after completing the contract or ceasing to furnish | AS 34.35.068(a) |
| After a notice of completion | 15 days for claimants with advance notice or no notice of right to lien | AS 34.35.068(b) |
| Verification | Oath of the claimant or another person with knowledge | AS 34.35.070 |
| Duration | 6 months after recording unless suit is started or an extension recorded | AS 34.35.080(a) |
The recording deadline
Without a notice of completion, you have 120 days from completing your contract or your last furnishing. Once the owner records a notice of completion, check whether the 15-day rule applies to you. A claimant who has already recorded a notice of right to lien keeps the 120 days.
Contents of the claim
AS 34.35.070 lists what the claim must state: the property with a legal description, the owner, your name and address, the person who hired you, a general description of the work and the contract price, the amount due, and the date you last furnished labor, materials, services or equipment.
How LawVault handles Alaska
LawVault’s builder prepares a claim of lien for Alaska. It asks for:
- Your role: contractor hired by the owner, subcontractor, supplier or worker
- Your legal name, address and any license number
- The owner from the land records, the street address, parcel number and legal description
- Who hired you, the original contractor, the contract, what you furnished, your first and last dates of work and the amount after credits
- The date of any notice of right to lien you gave, if you were not hired by the owner
The finished document has a sworn verification with a notary jurat, a proof of service page and a guidance page that reminds you to confirm the recording deadline. Because a notice of completion can shorten Alaska’s window, check the land records before you rely on any date. The claim is printed and signed in ink, not e-signed. LawVault does not check whether you have lien rights or whether you are on time, and it never promises that a lien is valid.
Missing an Alaska deadline loses the lien. LawVault is a document service, not a law firm, and this page is not legal advice. Ask an Alaska construction attorney where to record and whether the owner must be served before you rely on the lien.
How to file an Alaska mechanic’s lien
- Check for a notice of completionSearch the land records; a recorded notice can cut your window to 15 days.
- Find your last work dateUse the day you completed your contract or stopped furnishing and count 120 days.
- Build the claimEnter the owner, legal description, hiring party, work, contract price, dates and amount due.
- Verify under oathPrint the claim and sign the oath, usually before a notary.
- Record the claimRecord the claim of lien for the property within your deadline.
- Sue within six monthsStart the enforcement action, or record an extension notice, within six months.
This page reflects the Alaska Statutes as of November 2026.
Common questions
If no notice of completion has been recorded, record the claim of lien no later than 120 days after you complete your contract or stop furnishing labor, materials, services or equipment (AS 34.35.068(a)). A recorded notice of completion can cut that to 15 days for some claimants (§ 34.35.068(b)).
After the owner records a notice of completion, claimants who had advance notice of the recording date, or who never gave a notice of right to lien, must record a claim of lien or a notice of right to lien within 15 days. Claimants who already recorded a notice of right to lien keep the 120-day window (§ 34.35.068(b)).
An optional written notice given to the owner before you furnish work, with the statutory warning. If you give it properly, the owner carries the burden in a foreclosure case to show it did not know of or consent to your work (AS 34.35.064).
Yes. It must be verified by the oath of the claimant or another person who knows the facts, and it must list the property, owner, claimant, hiring party, work, contract price, amount due and last furnishing date (AS 34.35.070).
Six months after recording, unless you start an action to enforce it in that time or record an extension notice, which adds six months (AS 34.35.080). Record a notice of the action to protect against later buyers.
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your mechanic's lien
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.