What is a California mechanic's lien?
A California mechanic's lien is a claim against private real property by someone who improved it and was not paid. The Civil Code calls the recorded document a claim of mechanics lien, and its contents are set by § 8416. Contractors, subcontractors, suppliers and laborers who furnish work on the project are the usual claimants.
The lien is only as good as its timing. California sets short windows to give notice, to record and to sue, and each one is a condition of the lien. Federal and state public projects work differently: claimants there look to payment bonds and stop payment notices instead of a lien on public land.
California mechanic's lien rules
California mechanic's lien at a glance
| Topic | Rule | Source |
|---|---|---|
| Document | Claim of mechanics lien, with the Notice of Mechanics Lien | Cal. Civ. Code § 8416 |
| Preliminary notice | Within 20 days of first furnishing; laborers exempt | Cal. Civ. Code §§ 8200, 8204 |
| Direct contractor deadline | Earlier of 90 days after completion or 60 days after a recorded notice of completion or cessation | Cal. Civ. Code § 8412 |
| Other claimants | Earlier of 90 days after completion or 30 days after a recorded notice | Cal. Civ. Code § 8414 |
| Verification | Signed and verified by the claimant; no acknowledgment needed | Cal. Civ. Code § 8416 |
| Service on owner | Copy mailed to the owner; no service makes the lien unenforceable | Cal. Civ. Code § 8416 |
| Suit to enforce | Within 90 days after recording | Cal. Civ. Code § 8460 |
The recording deadline
California counts from the completion of the whole work of improvement, not from your last day on site. A recorded notice of completion or cessation shortens the window: to 60 days for a direct contractor and to 30 days for everyone else. Check the county records for such a notice before you count.
A direct contractor also has to wait until it has finished its own contract before recording. Subcontractors and suppliers record after they stop providing work. A claim recorded too early or too late cannot be enforced.
Notices before and after recording
The 20-day preliminary notice goes to the owner, the direct contractor and any construction lender. If you send it late, your lien only covers work from 20 days before service onward.
After recording, mail a copy of the claim and its Notice of Mechanics Lien to the owner. Keep the certificate of mailing or the certified mail receipt as proof.
How LawVault handles California
LawVault’s builder prepares a California claim of mechanics lien. It asks for:
- Your role: contractor hired by the owner, subcontractor, supplier or worker
- Your legal name, address and any license number
- The owner from the land records, the street address, county, parcel number and legal description
- Who hired you, the original contractor, the contract, what you furnished, your first and last dates of work and the amount after credits
- The date of the preliminary notice you served, if any
The finished document has a sworn verification with a notary jurat, a page that marks where the statutory Notice of Mechanics Lien goes (attach the exact words of § 8416(a)(7) before you record; the builder does not reproduce them), a proof of service affidavit for the copy you mail the owner, and a guidance page with California’s recording rule. Because the deadline depends on completion of the whole project and on any recorded notice, it is not a simple day count, so the guidance page states the rule rather than a date. The claim is printed and signed in ink, not e-signed. LawVault does not check whether you have lien rights or whether you are on time, and it never promises that a lien is valid.
Missing any California deadline loses the lien. LawVault is a document service, not a law firm, and this page is general information about the Civil Code, not legal advice. For a large claim or a disputed project, speak with a California construction attorney before you record.
How to file a California mechanic’s lien
- Confirm your noticeCheck that you served a 20-day preliminary notice, or note which work it covers.
- Find your deadlineLook up the completion date and any notice of completion or cessation in the county records.
- Build the claimEnter the owner, legal description, hiring party, work, dates and amount owed.
- Sign and verifyPrint the claim and sign the verification in ink.
- Record and serveRecord with the county recorder and mail a copy with the Notice of Mechanics Lien to the owner.
- Sue within 90 daysFile an action to enforce the lien within 90 days after recording, or it expires.
This page reflects the California Civil Code as of November 2026.
Common questions
A direct contractor records after finishing its contract and before the earlier of 90 days after the whole project is completed or 60 days after the owner records a notice of completion or cessation. Subcontractors and suppliers record after they stop work and before the earlier of 90 days after completion or 30 days after such a notice (Civ. Code §§ 8412, 8414).
Most claimants do. Section 8204 requires the preliminary notice within 20 days after you first furnish work. A late notice still works, but only for work furnished in the 20 days before it was served and after. Laborers are exempt, and a claimant with a direct contract with the owner only has to notify the construction lender, if there is one (§ 8200).
No notary is required. Section 8416 says the claim must be signed and verified by the claimant, and the recorder accepts it without an acknowledgment. Verification means a sworn statement that the contents are true.
Yes. A copy of the claim, including the Notice of Mechanics Lien, goes to the owner or reputed owner by registered, certified or first-class mail with a certificate of mailing. Section 8416 makes a claim unenforceable if this service is not made.
You must file a lawsuit to enforce the lien within 90 days after recording the claim, unless you and the owner record an agreed extension of credit (Civ. Code § 8460). If you miss it, the lien expires.
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your mechanic's lien
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.