What is a Florida mechanic's lien?
Chapter 713 of the Florida Statutes lets unpaid contractors, subcontractors, suppliers and laborers claim a lien on the private property they improved. The recorded document is a claim of lien, and § 713.08 sets out what it must say and how it is signed.
Florida rewards claimants who keep their paperwork in order. Anyone without a contract with the owner sends a notice to owner early in the job, everyone records within 90 days of their last work, and the lien expires after a year without a lawsuit. Public projects are different: claimants there rely on payment bonds, not liens.
Florida mechanic's lien rules
Florida claim of lien at a glance
| Topic | Rule | Source |
|---|---|---|
| Document | Claim of lien | Fla. Stat. § 713.08 |
| Notice to owner | Within 45 days of starting, for lienors not in privity with the owner; laborers exempt | Fla. Stat. § 713.06(2)(a) |
| Recording deadline | Within 90 days after final furnishing | Fla. Stat. § 713.08(5) |
| Verification | Signed and sworn to or affirmed; statutory form has a notary jurat | Fla. Stat. § 713.08(2), (3) |
| Where to record | Clerk’s office of each county where the property sits | Fla. Stat. § 713.08(5) |
| Service on owner | Before recording or within 15 days after | Fla. Stat. § 713.08(4)(c) |
| Contractor affidavit | Final payment affidavit at least 5 days before suing | Fla. Stat. § 713.06(3)(d) |
| Suit to enforce | Within 1 year after recording; 60 days after a notice of contest | Fla. Stat. § 713.22 |
The recording deadline
Florida counts from your own final furnishing, not from completion of the whole project. Pick the last day you did contract work or delivered materials for the job, and count conservatively when in doubt.
Notices before and after recording
The notice to owner is the step subcontractors and suppliers miss most. Without it, a lienor who is not in privity with the owner generally has no lien. Laborers are exempt.
After recording, serve the claim of lien on the owner within 15 days if you did not serve it beforehand. A contractor in direct privity must also give the owner a final payment affidavit at least five days before filing suit.
How LawVault handles Florida
LawVault’s builder prepares a Florida claim of lien. It asks for:
- Your role: contractor hired by the owner, subcontractor, supplier or worker
- Your legal name, address and any license number
- The owner from the land records, the street address, county, parcel number and legal description
- Who hired you, the original contractor, the contract, what you furnished, your first and last dates of work and the amount after credits
- The date you served your notice to owner, if you needed one
The finished document has a sworn verification with a notary jurat, a proof of service page for the copy you serve on the owner, and a guidance page with Florida’s recording deadline. For a contractor hired by the owner, the guidance page estimates the 90-day date from your last furnishing date; subcontractors and suppliers count the same 90 days from their own final furnishing. The claim is printed and signed in ink, not e-signed. LawVault does not check whether you have lien rights or whether you are on time, and it never promises that a lien is valid.
Missing a Florida deadline loses the lien. LawVault is a document service, not a law firm, and this page is not legal advice. For a large or disputed claim, speak with a Florida construction attorney.
How to file a Florida mechanic’s lien
- Check your notice to ownerIf you had no contract with the owner, confirm your notice to owner went out within 45 days.
- Find your final furnishing dateUse the last day you did contract work or delivered materials.
- Build the claimEnter the owner, legal description, hiring party, work, dates and amount owed.
- Sign before a notaryPrint the claim and swear to it in front of a notary.
- Record and serveRecord with the county clerk within 90 days and serve the owner within 15 days.
- Sue within one yearFile suit to enforce the lien within a year, or 60 days after a notice of contest.
This page reflects the Florida Statutes as of November 2026.
Common questions
No later than 90 days after your final furnishing of labor, services or materials (Fla. Stat. § 713.08(5)). The same window applies to contractors, subcontractors and suppliers. A terminated contract can shorten it.
If you have no contract with the owner, yes. Section 713.06 requires lienors not in privity with the owner, other than laborers, to serve a notice to owner within 45 days after starting work or delivering materials, and before the owner’s final payment.
It must be signed and sworn to or affirmed by the lienor or an agent who knows the facts (§ 713.08(2)). The statutory form ends with a notary jurat, so you sign it before a notary.
Yes. Serve the owner before recording or within 15 days after recording. Late service can make the lien voidable to the extent it hurt someone who relied on it (§ 713.08(4)(c)).
One year after recording, unless you start a lawsuit to enforce it in that time. The owner can shorten that to 60 days by recording and serving a notice of contest (§ 713.22). A contractor must also deliver a final payment affidavit at least 5 days before suing (§ 713.06(3)(d)).
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your mechanic's lien
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.