What is a Louisiana statement of claim or privilege?
Louisiana does not use the phrase mechanic's lien in its statute. The Private Works Act, La. R.S. 9:4801 and following, gives subcontractors, laborers, suppliers of materials, lessors of equipment and professional consultants a claim against the owner and the contractor, secured by a privilege on the property where the work was done (9:4802). General contractors have their own privilege. To keep the claim and privilege alive, you file a statement of claim or privilege with the recorder of mortgages in the parish where the property is located.
The Louisiana system is built around two documents the owner may file. A notice of contract, filed at the start of the job, shortens some claimants' deadlines. A notice of termination, filed when the work is done or stops, starts the clock. If the owner files neither, the clock runs from substantial completion or abandonment of the work, not from your own last day on the job.
- A Louisiana statement of claim or privilege for a contractor, subcontractor, supplier or worker
- The property, the owner, who you worked for, and the amount and nature of the obligation, itemized
- A signature block for the claimant, with a notary block many recorders expect
- The Louisiana filing periods, the residential notice of nonpayment and the 1-year suit deadline on the signing page
- A proof of service page for the copy you deliver
Louisiana Private Works Act rules
Louisiana statement of claim or privilege at a glance
| Topic | Rule | Source |
|---|---|---|
| General filing period | 60 days after a notice of termination, or after substantial completion or abandonment if none is filed | La. R.S. 9:4822(A) |
| Notice of contract filed | Subcontractors, suppliers and others: 30 days after a notice of termination, or 6 months after substantial completion if none | La. R.S. 9:4822(B) |
| General contractor | Privilege preserved under 9:4811: 60 days after a notice of termination, or 7 months after substantial completion if none | La. R.S. 9:4822(C) |
| Residential, no notice of contract | 70 days if you gave the owner a notice of nonpayment at least 10 days before filing | La. R.S. 9:4822(D) |
| Contents | Written and signed; identifies the property and the owner; states the amount and nature of the obligation, itemized | La. R.S. 9:4822(H) |
| Copy to owner | Required when a notice of contract was filed with the owner's address | La. R.S. 9:4822(B) |
| Where to file | Recorder of mortgages of the parish where the property is located | La. R.S. 9:4831(A) |
| Suit to enforce | Within 1 year after filing the statement | La. R.S. 9:4823(A)(2) |
Read from the Louisiana Revised Statutes as published on FindLaw, shown as current as of January 1, 2023. Confirm the current text on the Louisiana Legislature's site before you file.
Which deadline applies to you
Start by checking the parish mortgage records for a notice of contract and a notice of termination on the property. If neither exists, most claimants file within 60 days after substantial completion or abandonment of the work. If the owner filed a notice of termination, the 60 days runs from that filing instead. When the owner timely filed a notice of contract, subcontractors, suppliers and other claimants under 9:4802 face the shortest window, 30 days after a notice of termination, or 6 months after substantial completion if no notice of termination is filed. A general contractor whose privilege was preserved under 9:4811 has 60 days after a notice of termination, or 7 months after substantial completion if none is filed.
Residential jobs have one more option. If no notice of contract was timely filed and you send the owner a written notice of nonpayment stating the amount and nature of what you are owed, before the normal 60-day period ends and at least 10 days before you file, you get 70 days to file. A claimant can also give the owner a written request to be told when the work is substantially completed or abandoned or a notice of termination is filed. The owner then has 10 days to tell you. If the owner does not and you miss the filing period, your claim against the owner survives if you sue within 1 year after the period ends, but the privilege on the property is still lost (9:4822(I), (J)).
How the builder handles Louisiana
The document is titled as a Louisiana statement of claim or privilege. It carries the claimant’s plain signature, with no oath and no penalty-of-perjury statement, and an optional notary acknowledgment with the note that a notary is optional in Louisiana, because recorders often expect an acknowledged filing. The signing page prints the Louisiana filing periods, the residential notice of nonpayment rule, the copy-to-owner rule and the 1-year deadline to sue. Because the clock starts with the owner's notice or with substantial completion of the whole job, the guidance page explains the rule instead of computing a date from your last day of work.
LawVault is a document service, not a law firm, and this page is not legal advice. The builder does not search the mortgage records, check whether you have a claim or privilege, or decide which filing period applies to you, and it cannot revive a claim filed too late. For a large claim, talk to a Louisiana construction lawyer.
Public projects in Louisiana follow a separate statute. Public property cannot be subject to a private privilege, so contractors on public work post payment bonds, and unpaid subcontractors and suppliers claim against the bond under its own rules.
How to file in Louisiana
- Search the mortgage recordsLook for a notice of contract and a notice of termination on the property at the parish recorder of mortgages.
- Find your filing periodUse the table above to pick your deadline: 30 days, 60 days, 6 months or 7 months, or 70 days with a residential notice of nonpayment.
- Enter the job and the amountAdd the owner, the property description, who you worked for, and an itemized amount and nature of what you are owed.
- Sign the statementPrint the statement, sign it, and have the notary block completed if your recorder expects it.
- File with the recorder of mortgagesFile in the parish where the property is located and deliver a copy to the owner, and to the contractor, as the rules require.
- Calendar the suit deadlineNote the date 1 year after filing and sue the owner before it passes.
Louisiana's Private Works Act rewards claimants who watch the public records. Keep your contract, invoices and delivery records together, check the mortgage records early, and file well inside your period. This page reflects the Louisiana statutes as published on FindLaw; check for amendments since January 2023.
Common questions
Louisiana uses the word privilege. Under the Private Works Act (La. R.S. 9:4801 and following), unpaid contractors, subcontractors, laborers, suppliers and others preserve their claim and privilege on the property by filing a written statement of claim or privilege with the parish recorder of mortgages.
It depends on what the owner filed. The general rule is 60 days after the owner files a notice of termination, or after substantial completion or abandonment if no notice is filed. If the owner filed a notice of contract, subcontractors and suppliers have 30 days after a notice of termination, or 6 months after substantial completion if none. A general contractor with a preserved privilege has 60 days after a notice of termination, or 7 months after substantial completion if none (La. R.S. 9:4822).
The statute as we read it requires the statement to be in writing and signed by the claimant or its representative (La. R.S. 9:4822(H)). It does not state an oath. Our document still prints an optional notary acknowledgment, because recorders and title examiners often expect an acknowledged filing.
When the owner filed a notice of contract that gives the owner's address, the claimant must deliver a copy of the statement to the owner (La. R.S. 9:4822(B)). Delivering the statement to the contractor within the filing period also protects your claim against the contractor (9:4823(B)).
You must sue the owner to enforce the claim or privilege within 1 year after filing the statement. Otherwise it is extinguished (La. R.S. 9:4823(A)(2)).
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your mechanic's lien
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.