Step 1 of 5 · Getting Started

Free Mississippi Mechanic's Lien Form

Your answers save as you go. Legal form tools, not legal advice.

Free template

Download a free mechanic's lien template

Free blank form—no account or payment required. The PDF is printable and the Word file is editable. This general version does not include state-specific clauses or disclosures.

Build a guided Mississippi version
Real EstateLast updated November 12, 20264 min read

What is a Mississippi mechanic's lien?

Mississippi rewrote its construction lien law in 2014. Article 21 of Title 85, Chapter 7 (§§ 85-7-401 to 85-7-433) lets unpaid contractors, subcontractors, suppliers and design professionals file a claim of lien against the private property they improved.

The rules are short and strict. Every claimant files within 90 days of their last work, mails copies within 2 business days, and sues within 180 days. Mississippi courts have read these sections literally, so small slips cost liens. Public projects are different: claimants there rely on payment bonds, not liens.

Mississippi mechanic's lien rules

Mississippi claim of lien at a glance

TopicRuleSource
DocumentClaim of lien, with the expiration statement and notice to owner the statute requiresMiss. Code Ann. § 85-7-405(1)(b)
Recording deadlineWithin 90 days after last work, labor, services or materialsMiss. Code Ann. § 85-7-405(1)(a)
Where to fileClerk of the chancery court of the county where the property sitsMiss. Code Ann. § 85-7-405(1)(a)
Copies after filingOwner, and the contractor if you are not the contractor, within 2 business days by registered or certified mail or statutory overnight deliveryMiss. Code Ann. § 85-7-405(1)(b)
Residential pre-lien noticeClaimants without a contract with the owner: Pre-Lien Notice at least 10 days before filingMiss. Code Ann. § 85-7-409
Suit to enforcePayment action within 180 days after filing, with a lis pendens filed at the same timeMiss. Code Ann. §§ 85-7-405(1)(c), 85-7-421
Notice of contestLien ends at the earlier of 90 days after the notice or 180 days after filing, unless suit is filedMiss. Code Ann. § 85-7-423

The recording deadline

Mississippi counts 90 days from your own last work, labor, services or materials on the job. Use the last day you did contract work or delivered materials, and file well before the 90th day.

What the claim must say

Section 85-7-405(1)(b) lists what the claim must contain in substance. It includes a statement that the claim of lien expires and is void 180 days after filing unless a payment action is filed, and a notice to the owner of the property. Leaving either out voids the lien. LawVault’s claim prints both, in our own plain wording of what the statute requires. Before you file, read that subsection and compare.

Notices before and after filing

On residential work covered by § 85-7-409, a subcontractor, supplier or design professional who has no contract with the owner must deliver a Pre-Lien Notice, in substantially the form in § 85-7-433(5), at least 10 days before filing. After filing, the 2 business day mailing rule applies to every claimant.

When you sue, file the lis pendens with the payment action. The Mississippi Supreme Court enforced that timing strictly in 2021, and a 2022 bill to soften it did not pass.

How LawVault handles Mississippi

LawVault's builder prepares a Mississippi claim of lien. It asks for:

  • Your role: contractor hired by the owner, subcontractor, supplier or worker
  • Your legal name, address and any license number
  • The owner from the land records, the street address, county, parcel number and legal description
  • Who hired you, the original contractor, the contract, what you furnished, your first and last dates of work and the amount after credits
  • The date you gave a Pre-Lien Notice, if you needed one

The finished document prints the 180-day expiration statement and the notice to owner of property. It carries your plain signature, with no oath and no penalty-of-perjury statement, and an optional notary acknowledgment with the note that a notary is optional in Mississippi, because clerks often expect one. It also has a proof of service page for the copies you mail and a guidance page with Mississippi's filing deadline. For a contractor hired by the owner, the guidance page estimates the 90-day date from your last furnishing date; subcontractors and suppliers count the same 90 days from their own last work. The claim is printed and signed in ink, not e-signed. LawVault does not check whether you have lien rights or whether you are on time, and it never promises that a lien is valid.

Ninety days to file, 180 days to sue

Missing a Mississippi deadline or a required statement can void the lien. LawVault is a document service, not a law firm, and this page is not legal advice. For a large or disputed claim, speak with a Mississippi construction attorney.

How to file a Mississippi mechanic's lien

  1. Check the pre-lien noticeOn residential work, a claimant without a contract with the owner needs a Pre-Lien Notice at least 10 days before filing.
  2. Find your last work dateUse the last day you did contract work or delivered materials.
  3. Build the claimEnter the owner, legal description, hiring party, work, dates and amount owed. The claim prints the statements § 85-7-405(1)(b) requires.
  4. Sign and fileSign the claim and file it with the chancery clerk within 90 days.
  5. Mail copies in 2 business daysSend the owner, and the contractor if that is not you, a true copy by registered or certified mail or overnight delivery.
  6. Sue within 180 daysFile the payment action and the lis pendens together within 180 days of filing.

This page reflects the Mississippi Code as enacted in 2014 and reported in late 2022.

Common questions

Ninety days after your last work performed, labor, services or materials provided (Miss. Code Ann. § 85-7-405(1)(a)). The same window applies to contractors, subcontractors and suppliers.

With the clerk of the chancery court in the county where the property is located (§ 85-7-405(1)(a)).

Yes, fast. No later than 2 business days after filing, mail a true copy to the owner by registered or certified mail or statutory overnight delivery. If you are not the contractor, send one to the contractor or its registered agent too (§ 85-7-405(1)(b)).

For residential work covered by § 85-7-409, a subcontractor, supplier or design professional who has no contract with the owner must give the owner a Pre-Lien Notice at least 10 days before filing. Without it there is no lien.

You must start a payment action within 180 days after filing and file a lis pendens with it, or the claim is unenforceable (§§ 85-7-405(1)(c), 85-7-421). If the owner or contractor records a notice of contest, the lien ends at the earlier of 90 days after that notice or the original 180 days unless you have sued (§ 85-7-423).

Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.

Still unsure? Visit the help center.

Ways to get your mechanic's lien

Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.

Free 7-day trial subscription Cancel anytime

$49/mo $0 for one week

Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.

Start 7-day trial

Pro, billed yearly

$9.99/moBest value · Save 80%

Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.

Start annual plan

Single document

$39One-time, no renewal

Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.

Build this document

Prices in USD. Free blank templates stay free. Compare plans or read the refund policy.

Build your mechanic's lien in minutes

Preview the document your answers produce — then review, e-sign, or download it.

State-specific · E-sign ready · Legal form tools, not legal advice