What is a Nevada mechanic's lien?
Nevada's mechanic's lien statute, NRS 108.221 to 108.246, lets contractors, subcontractors, suppliers and laborers claim a lien on property they improved. You perfect it by recording a notice of lien with the county recorder of the county where the property is located. NRS 108.226 sets the contents and a form, and the notice must be sworn.
Nevada stacks several notices on top of the lien itself. Depending on your role and the type of project, you may need a notice of right to lien early in the job and a 15-day notice of intent before recording.
Nevada mechanic's lien rules
Nevada mechanic's lien at a glance
| Topic | Rule | Source |
|---|---|---|
| Document name | Notice of lien | NRS 108.226 |
| Notice of right to lien | Required for claimants not in privity with the owner, except labor; covers 31 days back | NRS 108.245 |
| Residential notice of intent | 15-day notice to owner and prime contractor before recording, except laborers | NRS 108.226 |
| Recording deadline | 90 days after the latest of completion, your last delivery, or your last work | NRS 108.226 |
| Notice of completion | A valid, served notice of completion sets a 40-day window | NRS 108.226 |
| Signing | Verified by oath; acknowledgment not needed to record | NRS 108.226 |
| Service | Serve the owner within 30 days after recording | NRS 108.227 |
| Where to record | County recorder where the property is located | NRS 108.226 |
| Deadline to sue | 6 months after recording; one recorded extension up to 1 year | NRS 108.233 |
Notice of right to lien
If you contract with someone other than the owner and you supply materials, equipment, or work other than labor, you must give the owner a notice of right to lien in person or by certified mail. A subcontractor or supplier also sends a copy to the prime contractor for information. Without it you cannot perfect or enforce the lien for those items. The notice covers what you furnished in the 31 days before it is given and everything after, so send it at the start of the job. Prime contractors and others who contract directly with the owner do not need it.
Residential projects
For the construction, alteration or repair of single-family or multifamily residences, NRS 108.226(6) requires every lien claimant except laborers to serve a 15-day notice of intent to lien on the owner and the reputed prime contractor before recording. Service is by personal delivery or certified mail. Serving the notice extends the recording deadline by 15 days. This rule does not apply to nonresidential projects.
Recording, service and enforcement
Record the notice of lien within 90 days after the latest of the completion of the work of improvement, your last delivery of materials or equipment, or your last work. If the owner records and serves a valid notice of completion, a 40-day window runs from that recording. Knowingly making a false statement in a notice of lien is a gross misdemeanor.
Within 30 days after recording, serve a copy on the owner by personal delivery or certified mail, return receipt requested. NRS 108.227 lists fallback steps, such as posting the property, when the owner's addresses cannot be found. Then start a court action within 6 months after recording, or the lien stops binding the property.
How LawVault handles Nevada
The guided builder asks whether you are a contractor hired by the owner, a subcontractor, a supplier or a worker. It then collects the owner from the land records, the property's address, parcel number and legal description, who hired you, the work, your first and last furnishing dates, and the amount owed after payments and credits. It also asks what kind of building it is. If you were not hired by the owner, it asks whether you gave the notice of right to lien. On a residential job, it asks every claimant except a laborer for the date of the 15-day notice of intent.
The builder prints a Nevada notice of lien with a sworn verification and a notary's jurat, plus a proof of service page and a guidance page with the deadlines. Because a notice of completion can set a 40-day window, the guidance page states the rule and does not compute a date. The document is printed and signed in ink; it is not set up for e-signature.
Public projects
Liens generally cannot attach to public property. Federal projects use Miller Act payment bonds, and Nevada public works use bond protection under state law. If you worked on a public job, a bond claim is usually the remedy, not a lien.
This page explains Nevada mechanic's lien law in plain English. LawVault is a document service, not a law firm, and nothing here is legal advice. LawVault cannot promise your lien is valid or timely. If a notice of completion was recorded or the job is residential, check your dates with a Nevada attorney.
How to record a Nevada notice of lien
- Send the notice of right to lienIf you are not in a direct contract with the owner, give the notice early by hand or certified mail.
- Residential: serve the 15-day noticeServe the owner and prime contractor at least 15 days before you record.
- Prepare the notice of lienDownload the free Nevada template or answer the guided questions to build your notice of lien.
- Swear and recordVerify the notice under oath and record it with the county recorder within the deadline.
- Serve within 30 daysServe a copy on the owner by personal delivery or certified mail, return receipt requested.
- Sue within 6 monthsStart a court action within 6 months of recording, or sign and record an extension in time.
This page reflects the Nevada Revised Statutes as published on public.law. Check the current statute on the Nevada Legislature site before you file.
Common questions
Under NRS 108.226, within 90 days after the latest of the completion of the work of improvement, your last delivery of materials or equipment, or your last work. A valid notice of completion that was recorded and served properly sets a separate 40-day window, so watch for one.
Yes, if you did not contract directly with the owner and you supply materials, equipment or non-labor services. The notice goes to the owner in person or by certified mail, with a copy to the prime contractor. It reaches back only 31 days before it is given, so send it early.
On single-family and multifamily residential work, every lien claimant except laborers must serve a 15-day notice of intent to lien on the owner and the reputed prime contractor, by personal delivery or certified mail, before recording. Serving it extends the recording deadline by 15 days.
It must be verified by the oath of the lien claimant or another person, so you sign before an officer who can give oaths. NRS 108.226 says the notice does not need to be acknowledged to be recorded.
Six months after recording, unless you start a court action in that time. A recorded written extension, signed within the 6 months, can stretch it to no more than 1 year after recording.
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your mechanic's lien
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.