Step 1 of 5 · Getting Started

Free Oregon Mechanic's Lien Form

Your answers save as you go. Legal form tools, not legal advice.

Free template

Download a free mechanic's lien template

Free blank form—no account or payment required. The PDF is printable and the Word file is editable. This general version does not include state-specific clauses or disclosures.

Build a guided Oregon version
Real EstateLast updated November 12, 20265 min read

What is an Oregon mechanic's lien?

Oregon calls it a construction lien, and the document you file is a claim of lien. ORS Chapter 87 gives contractors, subcontractors, suppliers, equipment renters and laborers a lien on improvements they helped build. You perfect it by filing a verified claim with the recording officer of the county where the improvement sits.

Oregon's timeline is tight from start to finish. You have 75 days to file, 20 days after filing to notify the owner and lender, and 120 days after filing to sue.

Oregon construction lien rules

Oregon construction lien at a glance

TopicRuleSource
Document nameClaim of lienORS 87.035
Notice of right to lienCovers work from 8 business days before delivery; owner-requested work exemptORS 87.021
Filing deadline75 days after you stop furnishing or after completion, whichever is earlierORS 87.035
SigningVerified by oath of the filer or another person with knowledgeORS 87.035
Where to fileRecording officer of each county where the improvement is locatedORS 87.035
Notice after filingMail notice and a copy of the claim to owner and mortgagee within 20 daysORS 87.039
Notice before suitWritten notice of intent to foreclose at least 10 days before suitORS 87.057
Deadline to sue120 days after filing; 2-year cap with extended paymentORS 87.055

Notice of right to lien

Anyone who furnishes materials, equipment, services or labor for which a lien may be perfected must give the owner a notice of right to lien, unless the work was done at the owner's request. You can give it at any time, but it only protects what you furnished after the date eight days before it was delivered or mailed, not counting Saturdays, Sundays and legal holidays. The notice must substantially follow the form in ORS 87.023. On commercial improvements, those who perform labor on site, provide labor and material, or rent equipment do not need it.

What the claim must say

ORS 87.035 requires:

  • A true statement of your demand after deducting all just credits and offsets
  • The owner's name, or reputed owner's name, if known
  • The name of the person who hired you or to whom you furnished materials or rented equipment
  • A description of the property sufficient to identify it, including the address if known

Notice after filing and before suit

Within 20 days after filing, mail written notice of the claim to the owner and the mortgagee with a copy attached. Then, at least 10 days before you file a foreclosure suit, deliver a written notice of intent to foreclose to the owner and the mortgagee. Missing either step costs you your right to recover costs, disbursements and attorney fees.

The lien binds the property for 120 days after the claim is filed unless you sue within that time. If the claim states agreed extended payment terms, the 120 days run from the end of the extension, but no lien lasts more than two years after filing.

How LawVault handles Oregon

The guided builder asks whether you are a contractor hired by the owner, a subcontractor, a supplier or a worker. It then collects the owner from the land records, the property's address, parcel number and legal description, who hired you, the work, your first and last furnishing dates, and the amount owed after payments and credits. If you were not hired by the owner, it asks whether you gave the notice of right to lien. The notice of intent to foreclose comes later, before you sue, and is not part of the claim.

The builder prints an Oregon claim of lien with a sworn verification and a notary's jurat, plus a proof of service page and a guidance page with the deadlines. Because the 75 days run from your last furnishing or from completion of construction, whichever is earlier, the guidance page states the rule and does not compute a date. The document is printed and signed in ink; it is not set up for e-signature.

Public projects

Liens generally cannot attach to public property. Federal projects use Miller Act payment bonds, and Oregon public improvements use payment bonds under state law. If you worked on a public job, a bond claim is usually the remedy, not a lien.

Deadlines decide these claims

This page explains Oregon construction lien law in plain English. LawVault is a document service, not a law firm, and nothing here is legal advice. LawVault cannot promise your lien is valid or timely. Residential projects carry extra owner notice rules for contractors, so talk to an Oregon attorney about a home job.

How to file an Oregon claim of lien

  1. Send the notice of right to lienUnless the owner hired you directly, deliver or mail the notice early; it reaches back only 8 business days.
  2. Find your 75 daysCount from when you stopped furnishing or from completion of construction, whichever is earlier.
  3. Prepare the claimDownload the free Oregon template or answer the guided questions to build your claim of lien.
  4. Swear and fileVerify the claim under oath and file it with the county recording officer.
  5. Mail notice within 20 daysMail notice and a copy of the claim to the owner and the mortgagee.
  6. Sue within 120 daysDeliver a notice of intent to foreclose 10 days ahead, then sue within 120 days of filing.

This page reflects ORS Chapter 87 as published on public.law. Check the current statute on the Oregon Legislature site before you file.

Common questions

ORS 87.035 requires the claim of lien to be filed no later than 75 days after you stop providing labor, equipment or materials, or 75 days after completion of construction, whichever comes first.

Unless you furnished at the owner’s request, you usually do. The notice protects only what you furnished from eight days before it was delivered or mailed, not counting weekends and holidays. On commercial improvements, people who perform labor on site, provide labor and material, or rent equipment are exempt.

Yes. It must be verified by the oath of the person filing or of someone else with knowledge of the facts. False swearing carries criminal penalties.

Yes. Within 20 days after filing, mail a written notice to the owner and the mortgagee with a copy of the claim of lien attached. If you do not, you cannot recover costs, disbursements or attorney fees.

The lien binds the property for only 120 days after the claim is filed unless you sue in that time. At least 10 days before suing, deliver a written notice of intent to foreclose to the owner and the mortgagee.

Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.

Still unsure? Visit the help center.

Ways to get your mechanic's lien

Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.

Free 7-day trial subscription Cancel anytime

$49/mo $0 for one week

Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.

Start 7-day trial

Pro, billed yearly

$9.99/moBest value · Save 80%

Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.

Start annual plan

Single document

$39One-time, no renewal

Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.

Build this document

Prices in USD. Free blank templates stay free. Compare plans or read the refund policy.

Build your mechanic's lien in minutes

Preview the document your answers produce — then review, e-sign, or download it.

State-specific · E-sign ready · Legal form tools, not legal advice