What is a Pennsylvania mechanic's lien?
Pennsylvania's Mechanics' Lien Law of 1963, 49 P.S. § 1101 and following, lets contractors and subcontractors file a mechanics' lien claim against property they improved. Unlike most states, you file the claim with the prothonotary, the clerk of the court of common pleas, rather than with a recorder of deeds. Section 1503 lists what the claim must state, including whether you file as a contractor or a subcontractor.
Subcontractors have an extra step. A formal 30-day notice of intent to file must reach the owner before the claim is filed.
Pennsylvania mechanics' lien rules
Pennsylvania mechanics’ lien at a glance
| Topic | Rule | Source |
|---|---|---|
| Document name | Mechanics’ lien claim | 49 P.S. § 1503 |
| Subcontractor notice | Formal written notice of intent to file at least 30 days before filing | 49 P.S. § 1501 |
| Filing deadline | 6 months after completion of your work | 49 P.S. § 1502 |
| Where to file | Prothonotary of the county where the property is located | 49 P.S. § 1502 |
| Notice to owner | Serve written notice of filing within 1 month after filing | 49 P.S. § 1502 |
| Affidavit of service | File within 20 days after service, or the claim can be struck | 49 P.S. § 1502 |
| Deadline to sue | 2 years from filing, unless the owner extends it in writing | 49 P.S. § 1701 |
| Judgment | Verdict or judgment within 5 years of filing | 49 P.S. § 1701 |
The subcontractor's 30-day notice
If you are a subcontractor, give the owner formal written notice of your intent to file at least 30 days before you file. The notice must state your name, the person you contracted with, the amount claimed, the general nature of the labor or materials, the date your work was completed, and a description of the property. You may send it by first-class, registered or certified mail to the owner or the owner's agent, or have an adult serve it the way a writ of summons is served. Posting on the property is a fallback. Since the claim deadline is six months, send this notice well before month five ends.
Filing and the notice of filing
File the claim with the prothonotary within six months after the completion of your work. Within one month after filing, serve written notice of the filing on the owner, stating the court, term and number, and the filing date. An adult serves it in the same manner as a writ of summons in assumpsit, or, if that cannot be done, it is posted on a conspicuous public part of the improvement. Then file an affidavit of service, or the owner's acceptance of service, within 20 days after service.
Enforcing the claim
Start the action to obtain judgment within two years from the date you filed the claim. Only the owner, in writing, can extend that time. A verdict or judgment must be entered within five years of filing, or the claim is wholly lost.
How LawVault handles Pennsylvania
The guided builder asks whether you are a contractor hired by the owner, a subcontractor, a supplier or a worker, which matters because the claim must say whether you file as a contractor or a subcontractor. It then collects the owner from the land records, the property's address, parcel number and legal description, who hired you, the work, your first and last furnishing dates, and the amount owed after payments and credits. Because Pennsylvania requires the subcontractor's 30-day notice, the builder asks a claimant who was not hired by the owner for the date of that notice, and the claim recites it.
The builder prints a Pennsylvania mechanics' lien claim with your plain signature, with no oath and no penalty-of-perjury statement, and an optional notary acknowledgment with the note that a notary is optional in Pennsylvania, because filing offices often expect one. Pennsylvania practice or court rules may call for a verification, so ask the prothonotary. It adds a proof of service page and a guidance page with the deadlines. Because Pennsylvania counts in months from completion of your work, the guidance page prints the six-month rule instead of a computed date. The document is printed and signed in ink; it is not set up for e-signature.
Public projects
Liens generally cannot attach to public property. Federal projects use Miller Act payment bonds, and Pennsylvania public works use payment bonds under state law. If you worked on a public job, a bond claim is usually the remedy, not a lien.
This page explains the Pennsylvania Mechanics’ Lien Law in plain English. LawVault is a document service, not a law firm, and nothing here is legal advice. LawVault cannot promise your lien is valid or timely. Other notice rules can apply to large or residential projects, so talk to a Pennsylvania attorney about your job.
How to file a Pennsylvania mechanics' lien claim
- Mark your completion dateYour six months run from the completion of your work.
- Subcontractors: send the 30-day noticeGive the owner formal written notice of intent to file at least 30 days before filing.
- Prepare the claimDownload the free Pennsylvania template or answer the guided questions to build your claim.
- File with the prothonotaryFile in the county where the property is located within six months of completion.
- Serve and prove serviceServe notice of filing within one month, then file the affidavit of service within 20 days.
- Sue within 2 yearsStart the action within two years of filing and reach judgment within five.
This page reflects 49 P.S. as published in the FindLaw mirror. Check the current statute before you file.
Common questions
Section 1502 requires the claim to be filed with the prothonotary within six months after the completion of your work. The deadline is counted in months, so mark the date on a calendar rather than counting days.
Yes. Under § 1501, a subcontractor’s claim is not valid unless the subcontractor gave the owner formal written notice of intent to file at least 30 days before filing. The notice states who you are, who hired you, the amount, the work, the completion date and the property.
With the prothonotary, the clerk of the court of common pleas, in the county where the property is located.
Yes. Serve written notice of the filing on the owner within one month after filing, then file an affidavit of service within 20 days after service. Missing either is enough to strike the claim.
Start the action within two years from the date of filing, unless the owner agrees in writing to extend it. A verdict or judgment must follow within five years of filing, or the claim is lost.
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your mechanic's lien
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.