What is a Rhode Island mechanic's lien?
Rhode Island's mechanic's lien law is Chapter 34-28 of the General Laws. The key document is a notice of intention to claim a lien. You mail it to the owner and file a copy in the land evidence records of the city or town where the land is located. In Rhode Island, land records are kept by each city and town, not by the county.
The notice is only the first step. Rhode Island gives you just 40 days after recording to start a court case and file a lis pendens, so plan the lawsuit before you record.
Rhode Island mechanic's lien rules
Rhode Island mechanic's lien at a glance
| Topic | Rule | Source |
|---|---|---|
| Document name | Notice of intention to claim a mechanic’s lien | R.I. Gen. Laws § 34-28-4 |
| Deadline | Mail before or within 200 days after the work or materials | R.I. Gen. Laws § 34-28-4 |
| Delivery | Registered or certified mail, return receipt requested, to the owner of record | R.I. Gen. Laws § 34-28-4 |
| Signing | Executed under oath; form includes a notary clause | R.I. Gen. Laws § 34-28-4 |
| Where to file | Land evidence records of the city or town where the land is located | R.I. Gen. Laws § 34-28-4 |
| Returned notice | File with the returned envelope within 30 days, and within 200 days of mailing | R.I. Gen. Laws § 34-28-4 |
| Deadline to sue | Complaint and lis pendens within 40 days of recording | R.I. Gen. Laws § 34-28-10 |
The 200-day window
Mail the notice of intention to the owner of record before or within 200 days after you did the work or furnished the materials. Send it by prepaid registered or certified mail, return receipt requested, to the owner's last known residence or place of business, or to the property address if neither is known. For a lien against a tenant's interest, mail it to the lessee or tenant. File a copy in the land evidence records of the city or town.
Work and materials more than 200 days old are outside the lien. If you furnished work over a long project, file before your earliest unpaid work ages out.
Signing under oath
The notice must be executed under oath. The form in § 34-28-4 ends with a notary clause, so sign it in front of a notary.
The 40-day enforcement deadline
Within 40 days of recording the notice of intention, file both a complaint to enforce the lien and a notice of lis pendens. The complaint goes in the same day as the lis pendens or within seven days after it. Miss the 40 days and the lien is void and wholly lost as to work and materials furnished before the 200-day period.
How LawVault handles Rhode Island
The guided builder asks whether you are a contractor hired by the owner, a subcontractor, a supplier or a worker. It then collects the owner of record, the property's address, parcel number and legal description, who hired you, the work, your first and last furnishing dates, and the amount owed after payments and credits.
The builder prints a Rhode Island notice of intention with a sworn verification and a notary's jurat, plus a proof of service page for the mailing and a guidance page with the deadlines. For a contractor hired by the owner, the guidance page estimates a date 200 days after your last furnishing date. Earlier work can age out sooner, and the 40-day lawsuit clock starts at recording. The document is printed and signed in ink; it is not set up for e-signature.
Public projects
Liens generally cannot attach to public property. Federal projects use Miller Act payment bonds, and Rhode Island public works use payment bonds under state law. If you worked on a public job, a bond claim is usually the remedy, not a lien.
This page explains Rhode Island General Laws Chapter 34-28 in plain English. LawVault is a document service, not a law firm, and nothing here is legal advice. LawVault cannot promise your lien is valid or timely. Because the lawsuit must follow within 40 days of recording, line up a Rhode Island attorney before you record.
How to file a Rhode Island mechanic's lien
- Check your 200 daysWork and materials furnished more than 200 days before filing lose their lien.
- Prepare the noticeDownload the free Rhode Island template or answer the guided questions to build your notice of intention.
- Sign under oathSign the notice before a notary.
- Mail and recordMail it by registered or certified mail, return receipt requested, and record a copy in the city or town land evidence records.
- Handle a returned noticeIf it comes back, file it with the envelope within 30 days of the return.
- Sue within 40 daysFile the complaint and lis pendens within 40 days of recording the notice.
This page reflects the Rhode Island General Laws as published in the FindLaw mirror, current as of January 1, 2026. Check the current statute before you file.
Common questions
Section 34-28-4 requires the notice of intention to be mailed before or within 200 days after you did the work or furnished the materials, with a copy filed in the land evidence records. Work done more than 200 days before the filing loses its lien.
By prepaid registered or certified mail, return receipt requested, to the owner of record at the last known residence or place of business, or to the property address if neither is known.
Yes. Section 34-28-4 says the notice shall be executed under oath, and the statutory form includes a notary clause.
You have 30 days after it is returned, and no more than 200 days after mailing, to file the notice together with the returned envelope. Otherwise the lien is void.
Only 40 days. Under § 34-28-10, file the complaint and a notice of lis pendens within 40 days of recording the notice of intention. The complaint must be filed the same day as the lis pendens or within seven days after it.
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your mechanic's lien
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.