Real EstateLast updated November 12, 20265 min read

What is a Washington mechanic's lien?

A Washington mechanic's lien, called a notice of claim of lien, is a claim against real estate by someone who furnished labor, professional services, materials or equipment for an improvement and was not paid. The rules sit in Chapter 60.04 of the Revised Code of Washington.

Washington uses one clock for everyone: 90 days after you stopped furnishing. What changes by role is the pre-lien notice. Suppliers and others lower in the chain who skip the notice to the owner can lose most or all of their lien.

The claim must state your name, phone number and address, your first and last dates of furnishing, the person who owes you, a description of the property, the owner or reputed owner (or that the owner is unknown), and the principal amount claimed (RCW 60.04.091).

Washington mechanic's lien rules

Washington mechanic's lien at a glance

TopicRuleSource
DocumentNotice of claim of lienRCW 60.04.091
Pre-lien noticeWritten notice to the owner; lien covers only what was furnished from 60 days before it (10 days on a new single-family home)RCW 60.04.031
Exempt from noticeDirect contracts with the owner, laborers, and subcontractors hired by the prime contractor (except existing owner-occupied homes)RCW 60.04.031(2)
Owner-occupied homesLower-tier claimants must give notice; lien limited to what the owner still owed the prime contractorRCW 60.04.031(3)
Recording deadlineWithin 90 days after you stopped furnishingRCW 60.04.091
SigningUnder penalty of perjury and acknowledged before a notaryRCW 60.04.091
Where to recordCounty where the property is locatedRCW 60.04.091
Owner copyWithin 14 days after recording, by certified or registered mail or personal serviceRCW 60.04.091
Suit to forecloseWithin 8 calendar months after recording; serve the owner within 90 days of filingRCW 60.04.141

Lien statutes change. Confirm the current rule before you rely on any date.

The notice to owner and owner-occupied homes

The pre-lien notice works as a lookback. You can send it at any time, but your lien covers only what you furnished on or after 60 days before you mailed or delivered it. On new construction of a single-family residence, the lookback shrinks to 10 days. If you supply materials or equipment, send the notice as soon as you start.

Some claimants do not need the notice at all: those who contracted directly with the owner or the owner's agent, laborers whose claim is for labor only, and subcontractors who contracted directly with the prime contractor.

Existing owner-occupied homes have their own rule. A claimant who contracted directly with the owner-occupier needs no notice and has a lien for the full contract amount. Anyone else must give the owner-occupier notice, and the lien can be paid only from money the owner had not yet paid the prime contractor when the notice arrived.

The statutory form in RCW 60.04.091 also includes a sworn statement that the claim is not frivolous, is made with reasonable cause and is not clearly excessive. Claim only what you are owed.

How the LawVault builder handles Washington

The builder titles the document "Notice of Claim of Lien" and prints a statement under penalty of perjury, including the statement that the claim is not frivolous, is made with reasonable cause and is not clearly excessive, with a notary acknowledgment, the form Washington calls for. It asks for the owner from the land records, the property's legal description, who hired you, the work you furnished, your first and last dates of furnishing and the amount after credits, and, if you were not hired by the owner, whether you gave the notice to owner.

For a contractor hired by the owner, the guidance page computes an estimated recording date 90 days after your last furnishing date. It also prints the 14-day owner copy rule and the 8-month suit deadline, and the document includes a proof of service page for the copy you send the owner.

Not legal advice

This page explains RCW 60.04 in plain English. LawVault is a document service, not a law firm, and nothing here is legal advice. The builder does not check whether you have lien rights or whether you are on time, and it cannot make a late claim valid. Public and federal projects generally use payment bonds instead of liens. For a large claim, talk to a Washington construction lawyer.

How to file a mechanic's lien in Washington

  1. Check your noticeIf you are a supplier, equipment renter or lower-tier claimant, confirm when you gave the owner the notice of your right to claim a lien.
  2. Count 90 daysCount 90 days from the last day you furnished labor, services, materials or equipment.
  3. Build the claimAnswer the guided questions or download the free Washington PDF or Word file.
  4. Sign before a notarySign under penalty of perjury and acknowledge the claim before a notary.
  5. Record and serveRecord with the county where the property is, then send the owner a copy by certified or registered mail or by hand within 14 days.
  6. Calendar the suit dateFile suit within 8 calendar months after recording and serve the owner within 90 days after filing.

A Washington lien rewards early paperwork: a timely notice to owner, a claim recorded well inside 90 days and a suit filed before 8 months pass. This page reflects RCW 60.04 as read in November 2026.

Common questions

Record the notice of claim of lien no later than 90 days after you stopped furnishing labor, professional services, materials or equipment (RCW 60.04.091). The 90 days are a hard limit: no foreclosure suit can be maintained on a claim recorded late.

Yes. The claimant or an authorized person signs, states under penalty of perjury that the notice is true and correct, and acknowledges it under chapter 64.08 RCW, which means before a notary (RCW 60.04.091).

Suppliers, equipment renters and professional service providers usually do. Your lien covers only what you furnished on or after 60 days before you gave the owner written notice, or 10 days on new construction of a single-family residence. Claimants who contracted directly with the owner, laborers, and subcontractors hired by the prime contractor are exempt, with an exception for existing owner-occupied homes (RCW 60.04.031).

Yes. Within 14 days after recording, send the owner or reputed owner a copy by certified or registered mail or deliver it in person. If you miss this, you lose your right to recover attorney fees and costs from the owner (RCW 60.04.091).

Eight calendar months after recording, unless you file a foreclosure suit in superior court in the county where the property is within that time. You must then serve the owner within 90 days after filing suit (RCW 60.04.141).

Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.

Still unsure? Visit the help center.

Ways to get your mechanic's lien

Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.

Free 7-day trial subscription Cancel anytime

$49/mo $0 for one week

Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.

Start 7-day trial

Pro, billed yearly

$9.99/moBest value · Save 80%

Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.

Start annual plan

Single document

$39One-time, no renewal

Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.

Build this document

Prices in USD. Free blank templates stay free. Compare plans or read the refund policy.

Build your mechanic's lien in minutes

Preview the document your answers produce — then review, e-sign, or download it.

State-specific · E-sign ready · Legal form tools, not legal advice