What is a West Virginia mechanic's lien?
Article 2 of chapter 38 of the West Virginia Code gives contractors, subcontractors and suppliers who improve private property a lien for the unpaid price of their work. The recorded document is a notice of mechanic's lien, and the statute supplies the form it follows, including a sworn statement.
West Virginia uses one number for most claimants: 100 days to record. What starts the clock depends on your role. The time to sue is short, only six months after recording. Public projects are different: claimants there rely on payment bonds, not liens on public property.
West Virginia mechanic's lien rules
West Virginia notice of mechanic's lien at a glance
| Topic | Rule | Source |
|---|---|---|
| Document | Notice of mechanic’s lien | W. Va. Code § 38-2-8 |
| General contractor deadline | Within 100 days after completing its work under the contract | W. Va. Code § 38-2-8 |
| Subcontractor deadline | Within 100 days after completing the subcontract | W. Va. Code § 38-2-9 |
| Supplier deadline | Within 100 days after it stops furnishing materials, machinery or equipment | W. Va. Code § 38-2-11 |
| Notice to owner | Subcontractors and suppliers serve the owner within the same 100 days | W. Va. Code §§ 38-2-9, 38-2-11 |
| Verification | Sworn statement before a notary or other officer | W. Va. Code §§ 38-2-8, 38-2-9 |
| Where to record | Clerk of the county commission where the property sits | W. Va. Code §§ 38-2-9, 38-2-11 |
| Suit to enforce | Within 6 months after filing the notice of lien | W. Va. Code § 38-2-34(a) |
The recording deadline
A general contractor has 100 days after completing its own work under the contract. A subcontractor has 100 days after completing its subcontract, and a supplier has 100 days after it last furnished materials, machinery or equipment. If you are unsure which day counts, use the earliest date that could apply.
Serving the owner
Subcontractors and suppliers have a second job inside the same 100 days: giving the owner, or the owner’s authorized agent, a notice of the lien. The statute says to use a method the law allows for serving a legal notice or summons, so plain mail may not be enough. Keep proof of how and when the owner received it.
How LawVault handles West Virginia
LawVault’s builder prepares a West Virginia notice of mechanic’s lien. It asks for:
- Your role: contractor hired by the owner, subcontractor, supplier or worker
- Your legal name, address and any license number
- The owner from the land records, the street address, county, parcel number and legal description
- Who hired you, the original contractor, the contract, what you furnished, your first and last dates of work and the amount after credits
- How you will send the owner a copy
The finished document has a sworn verification with a notary jurat, a proof of service page for the copy you serve on the owner, and a guidance page with West Virginia’s recording deadline. For a contractor hired by the owner, the guidance page estimates the 100-day date from your last furnishing date; check it against the day you completed your contract work. The claim is printed and signed in ink, not e-signed. LawVault does not check whether you have lien rights or whether you are on time, and it never promises that a lien is valid.
Missing the 100-day window or the 6-month suit deadline loses the lien. LawVault is a document service, not a law firm, and this page is not legal advice. For a large or disputed claim, speak with a West Virginia construction attorney.
How to file a West Virginia mechanic’s lien
- Find your start dateUse the day you completed your contract or subcontract, or the day you last furnished materials.
- Build the noticeEnter the owner, legal description, hiring party, work, dates and amount owed.
- Sign before a notaryPrint the notice and swear to it in front of a notary.
- Record itRecord with the clerk of the county commission within 100 days.
- Serve the ownerSubcontractors and suppliers serve the owner within the same 100 days, using a method allowed for a legal notice or summons.
- Sue within six monthsStart a suit in circuit court within 6 months after recording.
This page reflects the West Virginia Code as of November 2026.
Common questions
100 days. A general contractor counts from completing its work under the contract (W. Va. Code § 38-2-8), a subcontractor from completing its subcontract (§ 38-2-9), and a supplier to a contractor or subcontractor from the day it stopped furnishing (§ 38-2-11).
Yes. Within the same 100 days, they must give the owner or the owner’s authorized agent a notice of the lien, served by a method the law allows for serving a legal notice or summons (§§ 38-2-9, 38-2-11).
Yes. The statutory notice of lien forms end with a sworn statement taken before a notary or another officer, so you sign in front of a notary (§§ 38-2-8, 38-2-9).
In the office of the clerk of the county commission for the county where the property is located (§§ 38-2-9, 38-2-11).
You must start a suit in circuit court within 6 months after filing the notice of lien. If you do not, the lien is discharged (§ 38-2-34(a)).
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your mechanic's lien
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.