What is a Wisconsin mechanic's lien?
Subchapter I of chapter 779 of the Wisconsin Statutes gives contractors, subcontractors, suppliers and workers who improve private land a construction lien. Wisconsin calls the filed document a claim for lien, and § 779.06 lists what it must contain.
Wisconsin stands apart in two ways. The claim is filed with the clerk of circuit court, not a register of deeds, and every claimant must serve a notice of intent on the owner at least 30 days before filing. Public projects work differently: claimants there rely on payment bonds, not liens on public property.
Wisconsin mechanic's lien rules
Wisconsin claim for lien at a glance
| Topic | Rule | Source |
|---|---|---|
| Document | Claim for lien | Wis. Stat. § 779.06 |
| Prime contractor notice | In the written contract or within 10 days after first furnishing, on small residential jobs | Wis. Stat. § 779.02(2)(a) |
| Subcontractor and supplier notice | Two signed copies to the owner within 60 days after first furnishing | Wis. Stat. § 779.02(2)(b) |
| Notice of intent | Served on the owner at least 30 days before filing | Wis. Stat. § 779.06(2) |
| Filing deadline | Within 6 months from your last labor, services or materials | Wis. Stat. § 779.06(1) |
| Signature | Signed by the claimant or attorney; need not be verified | Wis. Stat. § 779.06(3) |
| Where to file | Clerk of circuit court of the county where the land sits | Wis. Stat. § 779.06(1) |
| Copy to owner | Serve a copy of the filed claim within 30 days after filing | Wis. Stat. § 779.06(1) |
| Suit to foreclose | Within 2 years from the filing date | Wis. Stat. § 779.06(1) |
The filing deadline
Wisconsin counts six months from your own last day of labor, services or materials, not from completion of the whole project. Six months is a calendar period, not a set number of days, so count from the exact date and leave margin. The notice of intent has to be served at least 30 days before you file, which means the practical cutoff for that notice falls about five months after your last work.
Notices before and after filing
The preliminary notice rules apply to wholly residential projects with four or fewer family living units. A prime contractor who will use subcontractors or suppliers puts the statutory notice in its written contract or serves it separately within 10 days after first furnishing. Subcontractors and suppliers serve two signed copies of their own notice within 60 days. Laborers and claimants hired directly by the owner, other than prime contractors, are exempt, and so are nonresidential and larger residential jobs.
Every claimant, exempt or not, serves the 30-day notice of intent. Copies of any preliminary notice and of the notice of intent go with the claim when you file it, and a copy of the filed claim goes to the owner within 30 days.
How LawVault handles Wisconsin
LawVault’s builder prepares a Wisconsin claim for lien. It asks for:
- Your role: contractor hired by the owner, subcontractor, supplier or worker
- Your legal name, address and any license number
- The owner from the land records, the street address, county, parcel number and legal description
- Who hired you, the original contractor, the contract, what you furnished, your first and last dates of work and the amount after credits
- The date of any preliminary notice and the date you served your notice of intent
The finished document carries your plain signature, with no oath and no penalty-of-perjury statement, then an optional notary acknowledgment, a proof of service page for the copy you serve on the owner, and a guidance page with Wisconsin’s filing deadline and notice rules. Wisconsin does not require a notarized claim, so the notary block is optional here. Because the deadline is six months rather than a day count, the guidance page explains the rule instead of computing a date. The claim is printed and signed in ink, not e-signed. LawVault does not check whether you have lien rights or whether you are on time, and it never promises that a lien is valid.
A late notice of intent or a late claim can cost you the lien. LawVault is a document service, not a law firm, and this page is not legal advice. For a large or disputed claim, speak with a Wisconsin construction attorney.
How to file a Wisconsin mechanic’s lien
- Check your preliminary noticeOn a small residential job, confirm your 10-day or 60-day notice went to the owner on time.
- Serve the notice of intentServe the owner a written notice of intent at least 30 days before you plan to file.
- Build the claimEnter the owner, legal description, hiring party, work, dates and amount owed, and attach your notices.
- Sign the claimPrint the claim and sign it in ink. A notary is optional in Wisconsin.
- File and send a copyFile with the clerk of circuit court within 6 months of your last work and serve the owner a copy within 30 days.
- Sue within two yearsFile a summons and complaint to foreclose within 2 years of filing the claim.
This page reflects the Wisconsin Statutes as of November 2026.
Common questions
Six months from the date you last performed or furnished labor, services, materials, plans or specifications (Wis. Stat. § 779.06(1)). The same window applies to prime contractors, subcontractors and suppliers. Because a 30-day notice of intent has to come first, plan to serve that notice at least 30 days before the six months end.
A written notice served on the owner at least 30 days before you file. It briefly describes the claim, the amount and the land and improvement, and it is required even if you already gave a preliminary notice (§ 779.06(2)).
On wholly residential projects with 4 or fewer family living units, yes. They serve two signed copies of their notice on the owner within 60 days after first furnishing. A late notice covers only work done after the owner receives it. Nonresidential projects and larger residential projects are exempt (§ 779.02).
No. Section 779.06(3) says the claim must be signed by the claimant or an attorney and need not be verified. LawVault’s document still includes a notary block, which you can complete or leave blank.
You must bring a foreclosure action, by filing a summons and complaint, within 2 years from the date you filed the claim for lien (§ 779.06(1)). Serve the owner a copy of the filed claim within 30 days after filing.
Yes. The PDF and Word files are free to download without an account. The PDF is a printable blank, not a fillable form; use the Word file or the guided builder to type your terms.
Still unsure? Visit the help center.
Ways to get your mechanic's lien
Answer the questions and preview the finished document free. You pay only when you’re ready to download, print or e-sign it, and you can choose how.
Free 7-day trial subscription Cancel anytime
$49/mo $0 for one week
Unlimited access to 210+ legal documents for 7 days. After the trial it renews at $49 a month unless you cancel at least 24 hours before it ends.
Start 7-day trialPro, billed yearly
$9.99/moBest value · Save 80%
Unlimited documents and edits, e-signature for every party, and the freedom to amend and re-issue at any time. Billed $119.88 a year and renews annually. Cancel anytime.
Start annual planSingle document
$39One-time, no renewal
Unlock just this mechanic's lien: a permanent PDF download, printing, e-signature for every party and a tamper-evident audit trail, with no subscription.
Build this documentPrices in USD. Free blank templates stay free. Compare plans or read the refund policy.